Fundraising completed
Capital Renovation Project of the New Building of the National Children’s Specialized Hospital “Ohmatdyt”
Role of the Foundation
The Ohmatdyt – Healthy Childhood Foundation joined the hospital’s recovery as a financial partner. The Foundation funds the capital renovation of the new medical and diagnostic building through contracts awarded via the Prozorro system.
Project Financing
The project has been financing in stages, through advance payments and tranches, with financial and technical control at every stage.
To date, the Foundation has made seven advance payments.
After the fifth payment, the hospital warned of a possible pause in the works. According to the hospital, internal organizational processes could temporarily affect the construction pace.
To keep the renovation moving and avoid a pause in the works, the Foundation increased the advance payment from 30% to 40%, in line with the contract terms. We have now completed this final 40% advance payment, fully meeting its financial commitments.
Key Financing Stages:
As of today, the Foundation has fulfilled its financial obligations within the project.
(more details here)
Other Project Participants and Their Roles
Project Management Services (on behalf of the hospital)
The international engineering company Eptisa acts as the client’s representative in this project. It represents the hospital’s interests and coordinates all organizational processes throughout implementation.
Eptisa’s work on this project is funded by the World Bank. The company ensures that construction complies with approved design documentation and applicable building regulations.
Project Contractor
The hospital selected the contractor through an open procurement procedure in the Prozorro system.
The general contractor is RIOLA-MODUL LTD, a Ukrainian construction company responsible for carrying out the construction works in line with approved designs, technical solutions, and contract terms.
Technical Supervision
Technical supervision of the works is carried out by the engineering company AKADEM BUD. The company specializes in capital construction project supervision and monitors works at all stages — from planning to commissioning.
Author’s Supervision
The engineering company ARKON provides the author’s supervision, ensuring that the works follow the approved design solutions and original architectural concept.
About the Project
On July 8, 2024, as a result of a missile strike, the buildings of Okhmatdyt National Children’s Specialized Hospital — one of the key pediatric centers in Ukraine — were damaged. That day, the hospital suffered serious losses: people were killed, and part of the departments could not operate at full capacity.
Project Status
During construction, the project required updates to the design documentation. The revised documentation was approved on November 21, 2025, based on an expert assessment. The project also faced delays in the delivery of certain construction materials.
Taking these factors into account, the parties agreed to extend the completion deadline until March 31, 2026. This decision was formalized through an additional agreement.
The hospital has since initiated another update to the design documentation, which is currently under review.
All information related to procurement, contracts, and additional agreements is publicly available in the Prozorro system.
Donation Terms
Funds collected within this project are allocated to achieving the stated fundraising goal.
If the project cannot be fully implemented or the fundraising purpose becomes no longer relevant, the remaining funds may be used by the Foundation for other charitable projects in accordance with its statutory activities.
By making a donation, the donor agrees to the possible reallocation of funds and confirms that the donation is voluntary and non-refundable.